14-Jul-2026 09:05 AM
SUPPLY, DELIVERY, INSTALLATION AND COMMISSIONING OF HUMAN INTERFACE SCREEN FOR FLOWSERVE
| Project Name: SUPPLY, DELIVERY, INSTALLATION AND COMMISSIONING OF HUMAN INTERFACE SCREEN FOR FLOWSERVE |
| Description: SUPPLY, DELIVERY, INSTALLATION AND COMMISSIONING OF HUMAN INTERFACE SCREEN FOR FLOWSERVE |
| Item No. | UNSPSC | Lot Name | Lot Description | Quantity | Unit of Measure |
|---|---|---|---|---|---|
| 1 | 20101601 | Screens | PRELIMINARIES AND GENERAL Allow for site mobilization, preparation of engineering shop drawings, risk assessments, safety management plans, and technical method statements. | 1 | Lump Sum |
| 2 | 20101601 | Screens | PRELIMINARIES AND GENERAL Provision of structured on-site technical training for municipal staff covering HMI menu navigation, basic software operation, and diagnostic troubleshooting. | 5 | Number |
| 3 | 20101601 | Screens | DECOMMISSIONING WORKS Extraction, verification, and offline digital archiving of legacy HMI software applications, tag databases, and communication profiles. NB- The decommissioned HMI unit to remain with all it’s data uninterrupted. | 1 | Each |
| 4 | 20101601 | Screens | DECOMMISSIONING WORKS Electrical isolation, disconnection of 24VDC power and field communication networks, and removal of the existing legacy HMI unit from the panel | 1 | Each |
| 5 | 20101601 | Screens | DECOMMISSIONING WORKS Anti-static ESD packaging, tagging with hardware inventory identifiers, and safe handover of legacy hardware to designated client storage. | 1 | Each |
| 6 | 20101601 | Screens | EQUIPMENT SUPPLY & HARDWARE INSTALLATION Supply and delivery to site of a new SIMATIC HMI TP1200 Comfort Panel (6AV2124-0MC01-0AX0) or approved equivalent. | 1 | Each |
| 7 | 20101601 | Screens | EQUIPMENT SUPPLY & HARDWARE INSTALLATION Supply and installation of a rugged programming and troubleshooting machine as well as essential HMI hardware accessories, including an industrial screen protector, heavy-duty Cat6 PROFINET patch cables, and mounting gaskets. | 1 | Each |
| 8 | 20101601 | Screens | EQUIPMENT SUPPLY & HARDWARE INSTALLATION Mechanical modification of the existing panel door cutout, including the supply and installation of a Siemens-approved adapter plate to achieve an IP65 perimeter seal. | 1 | Each |
| 9 | 20101601 | Screens | EQUIPMENT SUPPLY & HARDWARE INSTALLATION Physical mounting of the new HMI unit into the control panel using standard tension clamps, and termination of 24VDC power and field network communication cables. | 1 | Each |
| 10 | 20101601 | Screens | SOFTWARE INTEGRATION &PROGRAMMING Migration, recompilation, and firmware optimization of the extracted source application within TIA Portal / WinCC Comfort to natively match the new HMI architecture. | 1 | Lump Sum |
| 11 | 20101601 | Screens | SOFTWARE INTEGRATION &PROGRAMMING Software configuration and network mapping of device ID tags, IP/PROFINET addresses, and Modbus registers to interface with the core pump PLC and Soft Starter. | 1 | Lump Sum |
| 12 | 20101601 | Screens | SOFTWARE INTEGRATION &PROGRAMMING Development and configuration of localized HMI specialized operational graphics screens for Flowserve pump control (including control interfaces, real-time sensor readouts, data logging, and alarm displays). | 1 | Lump Sum |
| 13 | 20101601 | Screens | TESTING AND COMMISSIONING Execution of Pre-Commissioning loop checks, grounding verification, and physical communication link testing. | 1 | Lump Sum |
| 14 | 20101601 | Screens | TESTING AND COMMISSIONING Live Site Acceptance Testing (SAT), including loop calibration checks, interlock trip testing, and live functional commissioning under actual pump operational loads. | 1 | Lump Sum |
| 15 | 20101601 | Screens | TESTING AND COMMISSIONING Handover of compiled O&M manuals, test/calibration certificates, and unencrypted source code backup files on a physical USB drive. | 1 | Lump Sum |